A successful precision rooftop HVAC helicopter lift requires perfect teamwork between the ground crew and the pilot. On May 16, 2026, Fair Lifts Helicopter Services paired up with JC Lane Co to finish a massive project at 1375 Seaboard Industrial Blvd in Atlanta, Georgia. Our team swapped out dozens of large commercial air conditioning units in a busy urban area. By choosing an aerial lift, we turned a slow and difficult job into a fast, safe, and simple operation.
JC Lane Co is a top mechanical contractor that cares deeply about quality. They always look ahead to prevent problems before they happen on a job site. For this project, they needed to replace 27 old units with 27 new ones. That meant our team had to handle a total of 54 precise aerial picks. Each of these heavy rooftop units weighed about 2,100 pounds. The building height was between 40 and 60 feet. Handling this volume of heavy machinery required a smart plan, great communication, and the right equipment.
The Challenges of Downtown Crane Restrictions

A heavy industrial air conditioning unit hangs suspended by rigging cables as the installation crew guides its path from the roof deck.
When mechanical companies plan a project like this, they usually look at ground cranes first. However, traditional cranes face major limits in a busy city like Atlanta. Setting up a large crane requires a lot of open space. The area around Seaboard Industrial Blvd is highly congested with local traffic, tight power lines, and nearby buildings. A crane would have blocked roads and disrupted local businesses for days or even weeks.
Getting street closure permits in a busy industrial zone is also slow and expensive. JC Lane Co wanted to avoid these headaches to protect their client’s bottom line. They needed a solution that would keep the project moving forward without ground delays. Fair Lifts provided the perfect alternative by taking the entire operation into the air. Our helicopter lift eliminated the need for heavy ground setup and kept the streets completely open.
Choosing a Powerful and Reliable Aircraft

The transparent bubble cockpit of the Aérospatiale SA 315B Lama gives the pilot maximum visibility during a precision rooftop HVAC helicopter lift.
To lift the 2,100-pound loads safely, we utilized a specialized aircraft for the job. Our team deployed the Aérospatiale SA 315B Lama. This helicopter has a long history of excellent performance. It was originally built to fly in high mountains where the air is very thin. It pairs a light, strong frame with a powerful turbine engine. This design gives the helicopter incredible lifting power and gives the pilot a clear view of the cargo hook below.
The clear view is vital when placing heavy objects onto narrow roof curbs. The pilot can see every inch of the movement. This ensures the unit lands exactly where it needs to go. The Lama can hold a rock steady hover even if the wind picks up. This level of control makes it the ultimate tool for a complex commercial HVAC swap.
Smart Logistics to Save on Project Costs

Technicians handle the main rotor blades during the on site setup process, a strategy that drastically reduced mobilization costs for the client.
Bringing a specialized helicopter to Atlanta can be expensive. The SA 315B Lama was located at its home base in Oklahoma. Flying the aircraft all the way to Georgia would have added high fuel and flight time costs to the project budget. To save money for JC Lane Co, the Fair Lifts team used a clever logistical workaround.
The maintenance crew completely dismantled the helicopter in Oklahoma. They carefully secured the main body, rotor blades, and parts onto a large transport truck. The truck then drove the helicopter directly to the Atlanta job site. Once it arrived, our technicians reassembled the aircraft right on the scene. This smart decision cut down on mobilization costs and allowed us to offer a top-tier aerial solution at an affordable price.
Step by Step Execution on the Ground and in the Air

Ground crew members work in perfect unison to steady a 2,100 pound rooftop unit as the aerial rigging line begins to lift.
Because the project took place in a busy area, safety planning was our top priority. Fair Lifts created a detailed Congested Area Plan. This plan was approved by the Federal Aviation Administration before the launch date. On the morning of May 16, the parking lot at 1375 Seaboard Industrial Blvd served as our main staging area. The ground was cleared, and the area was blocked off to keep people safe.
The Rigging and Lifting Process
Our ground crew worked side by side with the mechanical technicians from JC Lane Co. Before the helicopter started its engine, every lift was fully mapped out. The team used a highly efficient workflow to keep the aircraft moving without any wasted time.
- Pre-Rigging: The ground crew attached strong straps and cables to the old units on the roof so they were ready to hook up instantly.
- The Quick Disconnect: The helicopter hovered above the roof, hooked onto an old 2,100-pound unit, lifted it away, and set it down in the parking lot.
- The Precision Placement: The crew then hooked a new HVAC unit from the staging area. The pilot lifted it to the roof and lowered it gently onto the open curb.
This repeating cycle went flawlessly. By using the helicopter, each individual pick took only a few minutes. The speed of the aircraft allowed the crew to swap all 27 units in a single morning. A crane would have taken days to do the exact same amount of work.
An Excellent Outcome for a Great Client

The parking lot staging area at 1375 Seaboard Industrial Blvd showing rows of commercial Trane HVAC units prepared for the aerial swap.
Just a few short hours after the lifts began, the last new unit was safely resting on its roof frame. The helicopter landed, and the site was cleared. The entire job was finished ahead of schedule with zero safety issues. The busy industrial park returned to normal traffic immediately, and neighboring businesses never experienced any roadblocks.
The team at JC Lane Co was incredibly happy with how the morning went. Afterward, they shared their feedback with us, saying,
Everything went well yesterday, thank you guys for an excellent day.
This project showed how careful planning and smart choices can solve tough construction problems. Fair Lifts is proud to provide heavy-lift services that keep projects on time and on budget. When a job demands true precision, going airborne is the most efficient path to success.
Bring Speed and Precision to Your Next HVAC Lift
When access is limited, schedules are tight, or crane operations become impractical, helicopter lifting can provide a faster and more efficient alternative. Fair Lifts specializes in coordinating rooftop HVAC installations, equipment replacements, and complex aerial construction projects throughout the United States.
Call Ana Rachidi at (470) 462-2225 to discuss your project requirements and learn whether a helicopter lift is the right solution for your job site.